This portal provides complete transparency for the Premium Villas development project in Abuja, Nigeria, including security fencing, gatehouse construction, site preparation, and landscaping works.
| Description | Quantity | Unit |
|---|---|---|
| Materials | ||
| 9 inches blocks | 760 | pieces |
| 6 inches blocks | 184 | pieces |
| Cement | 94 | bags |
| Granite number 3 | 25 | tones |
| Sharp sand | 1 | truck |
| Planks | 40 | pieces |
| 2x3 wood | 30 | length |
| 3 inches nails | 1 | bag |
| 2 inches nails | 1 | bag |
| Bending wire | 1 | roll |
| 10 mm rods | 56 | length |
| 8 mm rods | 30 | length |
| Workmanship | ||
| Excavation | Included | |
| Level and casting | Included | |
| Iron works | Included | |
| Carpentry works | Included | |
| Setting of blocks | Included | |
| Labour Cost | ₦525,000 | |
| Description | Quantity | Unit |
|---|---|---|
| Materials | ||
| 9 inches blocks | 1,256 | pieces |
| 6 inches blocks | 184 | pieces |
| Planks sawing of 2 inches and 3 inches for capping | 64 | length |
| Marine board for gate pillars and beams decking | 16 | pieces |
| 3 inches nails | 2 | bags |
| 2 inches nails | 1 | bag |
| Concrete nails 2 inches | 4 | packs |
| Chipping half inches | 20 | tones |
| Granite number 3 | 25 | tones |
| 16 mm rods for pillars and beams | 18 | length |
| 12 mm rods for lintel and decking | 38 | length |
| 10 mm rods | 20 | length |
| 8 mm rods | 16 | length |
| Bending wire | 1.5 | rolls |
| Sharp sand | 4 | trucks |
| Stone dust | 1 | trip |
| Plastering sand | 2 | trips |
| Cement | 264 | bags |
| Workmanship | ||
| Blocks work, capping pillars boarding, casting with plastering | Included | |
| Labour Cost | ₦1,646,000 | |
| Total Labour Cost (Fence + Gatehouse) | ₦2,171,000 | |
| Description | Cost (₦) |
|---|---|
| Materials | |
| 3 by 1 1/2 square pipe | 84,000 |
| 1 by 1 square pipe | 42,000 |
| 2mm plate | 252,000 |
| 1.5mm plate | 152,000 |
| Cut of plate | 140,000 |
| Electrode | 10,000 |
| Transport | 20,000 |
| Total Material Cost | ₦700,000 |
| Labour | ₦300,000 |
| Grand Total | ₦1,000,000 |
| Description | Amount (₦) |
|---|---|
| Total Cost | 1,600,000 |
| Amount Paid | 400,000 |
| Balance | 1,200,000 |
| Material | Quantity | Unit |
|---|---|---|
| 9 inches blocks | 2,016 | pieces |
| 6 inches blocks | 368 | pieces |
| Cement | 358 | bags |
| Granite number 3 | 50 | tones |
| Sharp sand | 5 | trucks |
| Planks | 104 | pieces |
| 2x3 wood | 30 | length |
| 3 inches nails | 3 | bags |
| 2 inches nails | 2 | bags |
| Bending wire | 2.5 | rolls |
| Material | Quantity | Unit |
|---|---|---|
| 16 mm rods | 18 | length |
| 12 mm rods | 38 | length |
| 10 mm rods | 76 | length |
| 8 mm rods | 46 | length |
| Chipping half inches | 20 | tones |
| Stone dust | 1 | trip |
| Plastering sand | 2 | trips |
| Marine board | 16 | pieces |
| Concrete nails | 4 | packs |
| Material | Quantity | Unit | Unit Rate (₦) | Total Cost (₦) |
|---|---|---|---|---|
| 9 inches blocks | 2,016 | pieces | 700 | 1,411,200 |
| 6 inches blocks | 368 | pieces | 580 | 213,440 |
| Cement | 358 | bags | 9,500 | 3,401,000 |
| Granite number 3 | 50 | tones | 10,700 | 535,000 |
| Sharp sand | 5 | trucks | 35,000 | 175,000 |
| Planks | 104 | pieces | 2,700 | 280,800 |
| 2x3 wood | 30 | length | 900 | 27,000 |
| 3 inches nails | 3 | bags | 27,000 | 81,000 |
| 2 inches nails | 2 | bags | 27,000 | 54,000 |
| Bending wire | 2.5 | rolls | 12,000 | 30,000 |
| Subtotal | 6,208,440 | |||
| Material | Quantity | Unit | Unit Rate (₦) | Total Cost (₦) |
|---|---|---|---|---|
| 16 mm rods | 18 | length | 20,500 | 369,000 |
| 12 mm rods | 38 | length | 10,800 | 410,400 |
| 10 mm rods | 76 | length | 8,500 | 646,000 |
| 8 mm rods | 46 | length | 5,500 | 253,000 |
| Chipping half inches | 20 | tones | 9,500 | 190,000 |
| Stone dust | 1 | trip | 45,000 | 45,000 |
| Plastering sand | 2 | trips | 40,000 | 80,000 |
| Marine board | 16 | pieces | 3,200 | 51,200 |
| Concrete nails | 4 | packs | 15,000 | 60,000 |
| Subtotal | 2,104,600 | |||
| Total Materials Cost | ₦8,313,040 |
| 20% Contingency Fee | ₦1,662,608 |
| Total Project material Cost | ₦9,975,648 |
Project Start Date: August 12, 2025
7 days
Excavation, leveling, casting, and setting of blocks for fence
10 days
Blocks work, capping pillars boarding, casting with plastering
8 days
Installation of 3mm burglary fence with all materials
7 days
Final grading and leveling of the site
8 days
Planting, mulching, and irrigation provision
Secure payment options for project funding: